There has been a slight delay in the construction - we lost the builder for a while - but the aircon has gone into the cavity between the ceilings

 

 

some pretty big units

 

also the console is under construction in the control room

 

The mike lines are from - drum booth - vocal booth - main Studio - rec room next the the control room - plus additional lines from the live area adjacent to the studio which will be used for live concerts etc

Also the drum booth is nearing completion - when we first talked about the finish Kev showed me a room he liked that was done out in old timber and old rusty galvanised roofing iron - Kev and Jenny have added to that idea :):)

The iron is glued to the plywood backing

This is the look

Cheers John

 

 

 

Webmaster - johnsay